Westchester Power 2024 Request For Proposals for Accounts in NYSEG Utility Territory

The contract for Westchester Power municipalities in the New York State Electric & Gas (NYSEG) utility territory ends on November 30, 2024. Sustainable Westchester will issue an RFP through it’s agent, AUE/Transparent, in August 2024 for a supplier to service the territory starting December 1, 2024.

Corrections and modifications to ESA subsequent to posting

We’ll record anything found to  here and these will be incorporated into the final document)

Click here for cumulative redline

 

Redline notes

8/6 – initial redlines copied over from final revisions to recent Con Edison ESA edits. Most substantive change is the edits to Exhibit A for he clarifications for pass through transmission costs.

8/20 – adjusted 4.9.2 NYPPT included cost from $0.00440 to $0.00414.

ESA Downloads

Click here for the Westchester Power 2024 Con Edison Territory RFP
Click here for the 2024 NYSEG Territory ESA Template
Click here for the Initial CCA Framework Order
Click here for the CCA Framework Modification Order
Click here for the CCA Program Rules

 

RFP Clarifications:

Final bidding scope will include Bedford, North Salem and Pound Ridge.

Municipal Participation MOUs

These municipal participation MOUs commit the municipality to sign the associated Electric Service Agreement if an award is made to a responsive bidder. As they are executed we’ll update the list.

Town of Bedford
Town of North Salem
Town of Pound Ridge